East Bridge Road Construction

Problem:
Pre-cast bridge arches had to be set in difficult terrain and in winter conditions. The project required two moves, one in the fall and one in the winter.

Solution:
Barnhart planning and rigging were essential in completing the project in time.

Description:
The East Road Bridge Project was a road construction project to re-align East Rd by putting in a new bridge and flattening the road. The project required 2 moves, one in the winter, one in the fall. The major challenge came during the winter portion and it involved positioning in a very deep road cut to get close enough to the work. In the winter, we set eight 21 1⁄2 ton pre- cast bridge arches and in the fall we set the remaining four.